Humes Takes on the Challenge at Kōwhai Park
Humes takes on the challenge at Kōwhai Park
Construction is nearing completion on the Kōwhai Park Solar Farm at Christchurch Airport - which will be New Zealand’s largest solar farm when fully operational later this year.
| The 230-hectare site includes around 300,000 solar panels and is expected to generate up to 168MWp of electricity, enough to meet the annual needs of approximately 36,000 New Zealand homes. |
TH Civil, a good customer of Humes, has been carrying out much of the site’s trenching and groundworks, including more than 50km of trenching for the extensive cabling network. The company was also contracted to design and construct two critical medium-voltage (MV) external road crossings beneath Pound Road and Savills Road.
“TH Civil approached us for supply options for the crossings,” explains Simon Paterson Account Manager. “The original specification for services to go below the road was for a 710 diameter pipe, which is a specialised size and in small quantities is quite expensive. So we worked with the team to develop a solution that fitted their construction methodology and met the project’s programme and delivery requirements.”
The project is a good example of Humes working with a customer to find a practical solution on a large and technically demanding project - and contributing to the infrastructure supporting New Zealand’s growing renewable energy sector.
| Principal: | Lightsourcebp |
| Civil Contractor: | TH Civil |
| Project: | Kōwhai Park Solar Farm |
| Location: | Christchurch Airport |
| Product: | Humes Polyethylene Pipe (PE) 810mm |